Following the successful installation of a water mist system within a food production plant, Surefire were asked to submit a competitive quotation to replace the existing “closed protocol system”.

The client has experienced weekly false alarms and expensive callouts, which caused the business a great deal of disruption. After a lengthy site survey and tender process we commenced with the system replacement, but had to ensure the existing system remained live throughout the changeover process.

This was achieved through a fully programmed schedule and the entire system was replaced in 5 days. Contract Value £55k